Federal Hill Case Study
This complete renovation of a penthouse condo
in Federal Hill required a lot of planning. The condo was located on the roof of a four story building and the only
access was through the newly renovated main lobby of the building. Significant measures were taken every day to protect
the lobby floor including floor mats, drop cloths, and 1/4 plywood. Elevator pads were put up every day and all
tenants were notified when there would be days with a lot of noise. The street had to be closed on multiple occasions
so that large materials could be craned to the roof top. At the end of each day the lobby, hall, and elevator
had to be vacuumed and formally cleaned. The 2500 (sq.) ft. renovation was completed in 10 months and the lobby
is as beautiful as the day we started the renovation.